Roof Ridge and Its Ornments

Following the local architectural traditions when building a slate roof, we placed two symbolic ornments, one at each end of the roof ridge:

  • A stone cross (with even branches), and
  • A granite sphere or ball

Based on what we were able to gather from locals, slate artisans and the Internet, the stone cross on top of a slate roof, in the higher plateaux of the Auvergne region, is first and foremost a symbol of protection. Although its position and orientation seem to vary slightly depending on the area, in most cases, it appears to be facing West.

The cross is placed on top of the roof not as a sign indicating the occupants faith but as a ‘firewall’ against diseases, epidemics, fire and lightnings.  It is there to steer danger away from the house, a bit like a magical shield.

The granite or stone sphere, placed on top of the roof, is to bring prosperity and fertility, and keep misfortune away.

For more info on local and architectural characteristics of the Auvergne region, I recommend the following website:

(www.cezaliersianne.asso.fr)

The Last Slate… Almost

Another important milestone was reached today with the installation of the last slates and ridge stones of the roof.

The slate work started at the end of September with amazing weather. The contractor made really good progress for the first three to four weeks before hitting a standstill because of really bad weather. When the temperatures hover between 2 and 5°C and the Northerly wind blows, it is almost impossible to stay and work on the roof. Luckily, the rain and the wind eased off about 7 days ago providing enough of a window for the slate workers to finish up the roof.

Let’s hope for a few more days of nice weather so the macons can finish filling in the gaps between the slates and the top of the walls. The gutters and the covering of the second chimney with zinc sheets will also be done within the next few days, weather permitting.

As for the roof of the garage which will also be covered with slates, it will have to wait until next Spring. Since it is a much smaller area, it should not take more than two weeks to complete.